FPS Solar Thermal Power Plant. Spain

Spain
Client: Arenales Solar PS
Type of contract: Supply, engineering, supervision of the installation, testing and start-up and commissioning
Design tools: SMART PLANT 3D
Design codes: UNE-EN

Turnkey project for the fire extinction and detection system in the 50 MW Arenales Solar Power Plant located in the municipality of Morón de la Frontera (Seville).

Project data

Total Flooding Systems with automatic action by gaseous extinction agent, Novec, a non-toxic gas, compatible with the presence of human beings, one of the two gaseous extinction agents with greater safety of use with people.